Photo report of Van Raam expansion in Varsseveld

Van Raam is building a new hall next to its current premises in Varsseveld. The hall will be approximately 4500 m2 in size. Read more about the new building in the article 'Van Raam further expands in Varsseveld'. On this page you can see pictures of the realization of the new hall.


Calendar week 37 (2021)

This week there is again plenty of work on the expansion of Van Raam. The following work is taking place among others:

  • Installation work (cable ducts, toilets, ventilation)
  • Place front window frame service office
  • Laying underfloor heating on the first floor
  • Placing of plaster walls
installation work new building van raam varsseveld
placing plaster walls new hall van raam varsseveld
new hallway installation work van raam varsseveld
partitions new construction raam varsseveld
storey floor new hall van raam varsseveld
Plaster walls van raam varsseveld

Calendar week 33 (2021)

This week the concrete floor is poured in the new hall of van Raam.

Pouring concrete for new hall of Van Raam
Pouring concrete new hall Van Raam
Pouring concrete extension Van Raam Varsseveld
Pouring concrete in new hall Van Raam
Concrete floor for new hall of Van Raam Varsseveld
Concrete floor extension Van Raam Varsseveld

Calendar week 30 and 31 (2021)

The construction workers have started laying the floor heating and sealing the premises. All openings have been sealed with tarpaulin.

Extension Van Raam sealing tarpaulin
van raam extension covered with tarpaulin
extension van raam varsseveld floor heating laid
Floor heating extension van raam Varsseveld

Calendar week 29 (2021)

The construction of the new hall of Van Raam is progressing well. The walls are almost closed and in the left hall they started with laying the reinforcement of the concrete floor. Here will be laid the underfloor heating.

walls of new hall van raam
placing wall covering hall van raam
walls new hall van raam almost shut
hall van raam varsseveld almost shut
reinforcement for concrete floor hall van raam
new hall van raam varsseveld takes shape

Calender week 28 (2021)

This week we started with the placing of the side walls and the electrics.Gerben Schepers sent us a nice aerial photo where in the upper right corner you can see Van Raam and the construction of the extra hall. 

side wall extension Van Raam Varsseveld
side walls extension Van Raam Varsseveld
extra hall from the inside
Electricity extra hall Van Raam extra hall from the inside Varsseveld
shovel at work on extension Van Vaam
Van-Raam-and-construction-additional-hall-seen-from-the-air

Calendar week 26 and 27 (2021)

The past week the construction of the steel structure of the new hall of Van Raam has continued. Also, nets have been hung up to safely lay the roof panels, the laying of these has started.

Further construction steel structure extension van raam
extension van raam construction steel structure
crane extension van raam varsseveld
corner view extension van raam varsseveld
van raam extension hall varsseveld
corner view van raam varsseveld
steel structure from top van raam
roof sheets  van raam extension
view of new hall van raam
roof sheets van raam varsseveld building inside

Calendar week 25 (2021)

The second fire resistant partition wall was installed this week. In addition, construction continued on the steel structure and a second floor was installed. The employees placed a maypole.

construction of extension van raam varsseveld
extension of van raam varsseveld partition wall
extension of van raam varsseveld second floor
extension of van raam varsseveld steel construction
Maypole Van Raam new factory hall
Placing maypole at new factory hall Van Raam

Calendar week 24 (2021)

This week, work continued on the steel structure. The first fire resistant wall has also been placed.

Installation of steel construction extension van raam
placing steel construction van raam varsseveld
fire-resistant partition wall extension van raam varsseveld
placing fire resistant partition wall van raam varsseveld

Calendar week 23 (2021)

The formwork for the foundation has been removed again. This week the anchors were elevated and construction of the steel structure began.

placing anchors for expansion of Van Raam Varsseveld
Anchors for expansion of Van Raam Varsseveld
Installation of construction extension Van Raam Varsseveld
Installing steel construction for extension of Van Raam Varsseveld

Calendar week 22 (2021)

In week 22, the formwork was placed and the concrete poured for the new hall. 

Van Raam expansion placing formwork
Formwork Van Raam expansion
concrete pouring of Van Raam expansion
Van Raam expansion concrete pouring

Calender week 19 (2021)

The work of the expansion of Van Raam in Varsseveld started in early May 2021 with earthmoving.

New construction of additional hall Van Raam Varsseveld
Van Raam Varsseveld expands new premises
expansion Van Raam Varsseveld
expansion of van raam earthmoving